Verification Plan has 5 stages:
Definition Stage:
Define the scope of the Verification Plan by selecting the specific procedures to be tested. These procedures form the basis for creating detailed test requests.
Approval Stage:
Assign a Person in Charge (PIC) responsible for approving the plan. The assigned PIC will receive an automated email notification prompting them to review and approve the verification plan.
Resource Allocation Stage:
Allocate the necessary resources required for testing. This includes adding Test Articles, Equipment, Technicians, and Facilities to ensure all elements are prepared for execution
Tracking Stage:
Monitor the progress of test requests generated from the plan. This stage provides real-time updates on the status, ensuring that all tests are on schedule and any issues are identified promptly.
When all the test requests created from the verification plan are marked as completed in the Test Request module, the Plan inCharge (PIC) will be able to mark the verification plan as complete.